Real Property Operations Detachment Petawawa will be conducting a planned electrical power shut-downs on April 3, 4, 5 and 6 in order to perform upgrades to Garrison high voltage distribution infrastructure. 

The shut-downs April 3, 5 and 6 will be from 0600 hrs until approximately 1700 hrs. The shut-down April 4 will be from 0600 hrs until approximately 1830 hrs.

APRIL 3 - 2 RCHA: P-115, P-114, P-113; 3 RCR: S-118; Gn Fire hall: S-665, S-105; Gn HQ: S-113, P-142; Gn HQ/RPOU/4 CDSG Sigs: S-111; and RPOU: S-41, S-114, S-124.

Temporary interruptions, at the commencement and conclusion of work, will affect the following buildings and complexes: 1 RCR: Y-101, Y-102; 2 CMBG HQ & Sigs: H-1; 2 CMBG: Z-101; 2 MPU: N-104; 2 RCHA: P-115, Z-104, Z-105, Z-117, Z-120, Z-133, Z-649; 2 Svc Bn: D-104, D-105, D-106, D-107, D-55, D-57, D-623, D-624, D-625, D-9, H-104, H-110, H-112, H-114, H-118, H-120, H-121, H-127, H-16, H-619, H-621, H-622, H-645, H-646, K-101, K-102, L-1, L-108, L-54, L-57, O-104; 3 RCR: S-118; 4 Cdn Div TC: H-107, H-124, M-104, N-107, O-9; 4 CDSG Sig Sqn: AA-18, B-16, H-101, H-111, H-119, L-109; Accommodations: F-16, G-101, G-102, G-106, J-103, J-108, L-101, L-103, L-104, N-103, P-101, P-50; B Foods: G-104; CFJSR: O-106; Gn Fire hall: AA-1, D-20; Gn HQ: L-106;Gn Ops  B-21, C-104, Y-103, Y-104; Museum: P-51; OTHER:    AA-20, AA-25, H-35, M-101, M-105, M-628, M-653, M-654, M-655, M-656, M-657, M-663, N-106, Z-106, Z-108, Z-608, Z-644, Z-684; PSP: C-102, D-19, D-2, J-106, L-105; and RCD : B-101, B-102, B-104, C-103, C-39, C-40, C-50, C-53, C-57, F-104, G-22; RPOU: AA-19, P-49.

APRIL 4 - 2 Fd Amb/Dental: N-113, P-144; 2 MPU: P-123, P-57663-PT; Accommodations: P-102; Gn HQ: Q-104, Q-101; Gn HQ/Gn MPs: P-105; Gn HQ/NPF: P-106; Gn HQ/PSP: Q-103; Gn Ops: P-141; Gn Ops/PSP: P-119; JPSU: P-143; and PSP: S-117, P-117, P-118.

APRIL 5 - 2 Fd Amb/Dental: N-113, P-144; 2 MPU: P-123, P-57663-PT; Accommodations: P-102; Gn HQ: Q-104, Q-101; Gn HQ/Gn MPs: P-105; Gn HQ/NPF: P-106; Gn HQ/PSP: Q-103; Gn Ops: P-141; Gn Ops/PSP: P-119; JPSU: P-143; and PSP: S-117, P-117, P-118.

APRIL 6 - 2 Fd Amb/Dental: N-113, P-144; 2 MPU: P-123, P-57663-PT; Accommodations: P-102; Gn HQ: Q-104, Q-101; Gn HQ/Gn MPs: P-105; Gn HQ/NPF: P-106; Gn HQ/PSP: Q-103; Gn Ops: P-141; Gn Ops/PSP: P-119; JPSU: P-143; and PSP: S-117, P-117, P-118.

RP Ops creates detailed plans to minimize affected users, however occasionally unforeseen circumstances/emergencies may arise where buildings other than those identified may be affected. If there are any power outages at any areas or buildings outside of this list, please inform the RP Ops Det Petawawa Trouble Desk at local 5588 or the Duty Engineer after hours (via Fire hall x 5555).

This power outage will not affect the RHUs.

POC: WO SC Mitchell, Works WO at local 6049.